Ankara–Samsun Motorway

The Ankara–Samsun Motorway is a 381-kilometre (237 mi) motorway partially under construction, consisting of Ankara–Delice and Delice–Samsun sections. Ankara-Delice section of the motorway is currently under construction as of 2025, and Delice-Samsun section is planned to be opened in 2035.

History

The Ministry of Transport and Infrastructure was going to make the tender of motorway via build-operate-transfer model, on 24 July 2022.[1][2][3] The “Tender for the Construction, Operation and Transfer of Ankara-Kırıkkale-Delice Motorway Project with Build-Operate-Transfer Model”, which was announced on 15 June and scheduled for 24 August, was postponed to 5 October 2022. [4] But the Ministry of Transport has delayed the tender to 15 December 2022 first, and then to 15 December 2023.[5] The construction protocol for the motorway was signed on 14 October 2024.[6]

Major intersections

Ankara–Kırıkkale–Delice section

District km Type Destinations Notes
Mamak 0.0 K1 Mamak O-20 Interchange O-20 / E88
1.5 V1 Viaduct 659 m
5.0 Motorway Service Area
Mamak 6.0 K2 Mamak (K2) Junction
10.0 V2 Viaduct 185 m
11.9 Pay Toll
Elmadağ 16.5 K3 Elmadağ Junction D.200
21.4 V4 Viaduct 185 m
23.8 V5 Viaduct 185 m
24.4 V6 Viaduct 185 m
33.7 T1 Tunnel 1280 m
35.4 V7 Viaduct 185 m
36.9 T2 Tunnel 1255 m
39.0 V7/A Viaduct 185 m
39.6 T3 Tunnel 475 m
40.1 T4 Tunnel 878 m
Yahşihan 45.0 K4 Yahşihan Junction
49.2 V8 Viaduct 185 m
Kırıkkale 50.5 K5 Kırıkkale West Junction D.765
52.0 Motorway Service Area (B Type)
Kırıkkale 69.5 K6 Kırıkkale East Junction D.200
83.0 Motorway Service Area
Delice 99.5 K7 Yozgat Interchange D.200 / E88

Delice–Samsun section

District km Type Destinations Notes
Delice 99.5 K7 Yozgat Interchange D.200 / E88
123.8 Motorway Service Area D Type
Sungurlu 138.4 K8 Sungurlu Junction D.190
141.7 Motorway Service Area B Type
Sungurlu 157.4 K9 Boğazkale Junction D.190
161.9 Motorway Service Area D Type
178.4 Motorway Service Area B Type
183.6 Viaduct 900 m
205.9 Motorway Service Area D Type
Çorum 210.7 K10 Alaca Junction D.795
233.3 Motorway Service Area A Type
Mecitözü 243.0 K11 Mecitözü Junction D.180
257.9 Motorway Service Area B Type
273.5 Motorway Service Area D Type
Merzifon 299.3 K12 Merzifon Junction D.100 / D.795 / E80
300.6 Motorway Service Area B Type
302.4 Tunnel 6600 m
309.1 Viaduct 435 m
309.7 Tunnel 855 m
310.6 Viaduct 210 m
Havza 313.1 K13 Havza Junction
314.5 Viaduct 575 m
323.2 Motorway Service Area D Type
328.6 Viaduct 645m
335.3 Tunnel 2965 m
350.1 Motorway Service Area D Type
363.3 Tunnel 565 m
364.3 Tunnel 1935 m
368.8 Viaduct 210 m
İlkadım 380.5 K14 Samsun Junction D.010 / E70

References

  1. ^ "Ulaştırma ve Altyapı Bakanlığı ihalesi yapılacak iki otoyola ilişkin detayları paylaştı". Anadolu Ajansı. Archived from the original on 17 June 2022. Retrieved 1 August 2022.
  2. ^ "Ankara-Kırıkkale-Delice otoyolu için düğmeye basıldı". Sabah (in Turkish). Archived from the original on 16 June 2022. Retrieved 2 August 2022.
  3. ^ "İki otoyol için ihale yapılacak". NTV (in Turkish). Archived from the original on 15 June 2022. Retrieved 2 August 2022.
  4. ^ leventelmastas (15 August 2022). "Antalya Alanya ve Ankara Kırıkkale Delice Otoyol İhaleleri Ertelendi". RayHaber | RaillyNews (in Turkish). Archived from the original on 15 August 2022. Retrieved 17 August 2022.
  5. ^ "İki otoyol ihalesi yine ertelendi". Bloomberght.com (in Turkish). 12 December 2022. Archived from the original on 12 December 2022. Retrieved 4 February 2023.
  6. ^ "Ankara-Kırıkkale-Delice ve Antalya-Alanya otoyol projelerinin yapımı için imzalar atıldı". Anadolu Ajansı. 14 October 2024. Retrieved 21 October 2024.